Overview
The City of Roseville manages a comprehensive Pavement Management Program (PMP) which includes repaving several miles of local streets annually. In 1986, Roseville began a program to reconstruct substandard residential streets. The PMP upgrades streets by neighborhood based on street condition.
To see which streets are scheduled to be repaved and have utility work done this summer, please see the 2023 Proposed PMP Project Map. Note that road segments have been removed from the original scope and may be further reduced based on project costs.
The majority of the roadways will have the top two inches of pavement removed and repaved (mill and overlay). In addition to the street resurfacing work, some curb and gutter will be replaced. Curb ramps for pathways will be upgraded to meet ADA. Minor utility repairs in the area will be performed with this project.
The cost of this project is funded by existing City funds. There will be NO ASSESSMENTS for this work.
Schedule
July 24 - Begin repairs to pedestrian ramps, utilities, and curb & gutter
September 11 - Begin mill and overlay
Please note, the schedule is weather-dependent and is subject to change.